Restoration of 27162 (4)

 

Work on the framework has continued and the east side frame and cantrail has been fitted. The west side is currently being prepared in the workshop. The gangway end has been refurbished and fitted temporarily to determine the position of the bolt holes.

In the meantime much effort . . . → Read More: Restoration of 27162 (4)

Progress 27001 18th Sept 2012

Two tasks were progressed today on the Brake Third.

Much grinding, hammering and chiselling was applied to one of the vertical frame supports, which needs to be removed in order to facilitate the wider window reveal, for the proposed extra seating bay.

This was the second day of work on this item, and finally the . . . → Read More: Progress 27001 18th Sept 2012